totalling about 138 typical activities
Home buying and renovation program
in mpp format at $8-60
____________________
totalling about 140 activities
Single storey brick building program
in mpp format at $8-80
____________________
totalling about 210 activities
Double storey brick building program
in mpp format at $9-60
____________________
Even more about these program examples ……
With these model programs along with the book Program_Your_Project you will be able to draft your project program in much detail and be able to do time and cost analysis throughout the project life cycle.
totalling to about 138 typical activities
Home buying and renovation program
in mpp format at $8-60
The home buying project program covers all the phases and aspects of a typical home buying and renovating project totalling to about 138 typical activities. With this model program along with the book Program Your Project you will be able to draft your project program in much detail and be able to do time and cost analysis throughout the project life cycle. The project phases and activity headings are as follows:
Planning to buy and renovate
Project concept
Planning renovations and additions if required
Procurement
Procurement of building construction services
Construction of renovations and additions
Site preparation
Foundation and slab
Certificate and Payment No.1
Builders registration council payment
Superstructure and Services first fix to roof wall plate height
Certificate and Payment No.2
Roof
Plaster and Screed
Ceilings
Certificate and Payment No.3
Plumbing fittings
Painting
Glazing
Electrical wiring and fittings
Finishing carpentry
Certificate and Payment No.4
Cabinet making
Metal work
Wall and Floor finishes
Site finishes
Ready for occupation and handover to owner
Practical Completion Certificate and Payment No.5
Deployment
Loose standing interior decorating
Occupy additions
Final Certificate and Payment No.6
totalling to about 140 activities
Single storey brick building program
in mpp format at $8-80
This building project program cover all the phases and aspects of a typical double storey home building project totalling to about 140 activities. With this model program along with the book Program Your Project you will be able to draft your project program in much detail and be able to do time and cost analysis throughout the project life cycle. The project phases and activity headings are as follows:
Planning
Project concept
Project definition
Project design
Procurement
Procurement of building construction services
Construction
Confirm material selections and order material and labor to suit program
Site preparation
Foundation and slab (conventional)
Certificate and Payment No.1
Builders registration payment
Superstructure and Services first fix to roof wall plate height
Certificate and Payment No.2
Roof
Plaster and Screed
Ceilings
Certificate and Payment No.3
Plumbing fittings
Painting
Glazing
Electrical wiring and fittings
Finishing carpentry
Certificate and Payment No.4
Cabinet making
Metal work
Wall and Floor finishes
Site finishes
Ready for occupation and building handover to owner
Practical completion certificate and Payment No.5
Deployment
Loose standing interior decoration
Occupation
Final Certificate and Payment No.6
totalling to about 210 activities
Double storey brick building program
in mpp format at $9-60
This building project program covers all the phases and aspects of a typical double storey home building project totalling to about 210 activities. With this model program along with the book Program Your Project you will be able to draft your project program in much detail and be able to do time and cost analysis throughout the project life cycle. The project phases and activity headings are as follows:
Planning
Project concept
Project definition
Project design
Procurement
Procurement of building construction services
Construction
Confirm material selections and order material and labor to suit program
Site preparation
Site wall
Foundation and ground floor (GF) slab (Soil mattress and raft)
Certificate and Payment No.1
Builder registration payment
Ground floor Superstructure
Certificate and Payment No.2
First floor (FF) Slab
First floor Superstructure
Certificate and Payment No.3
Roof
Plaster
Floor screeds
Ceilings
Certificate and Payment No.4
Plumbing fittings
Painting
Glazing
Electrical wiring and fittings
Finishing carpentry
Certificate and Payment No.5
Cabinet making
Metal work
Wall and Floor finishes
Site finishes
Ready for occupation and building handover to owner
Practical completion certificate and Payment No.6
Deployment
Loose standing interior installations
Occupation
Final Certificate and Payment No.7